Friday, October 24, 2014

Case Study: Grinder Pumps Fuel Economic Growth

Southside sits in a rural area of Arkansas. Residents relied on septic tanks, which had a number of problems: some were a half-century old and ending their useful life, but more so, the shallow, soggy soil didn't perc well ... vital for septic systems.
Credit: Crist Engineers

"Improving the wastewater system represents the absolute top priority," was the urgent message of the 2009 Batesville Comprehensive Plan.

"Existing subdivisions couldn't grow anymore and were becoming unsafe due to raw sewage because of bad percolation," says Richardson. A new collection system was fundamental, he adds, "for growth both residential and commercial."
Credit: Crist Engineers


A gravity sewer system would have cause massive disruption and deep trenches. Crist Engineers, located in Little Rock, had designed pressure sewer systems before and chose E/One grinder pumps to do the job.

What were the results? Read the entire story on E/One's web site.


Wednesday, October 22, 2014

Case Study: Town of Jerusalem, New York



The Town of Jerusalem is located in the Finger Lakes region of upstate New York. The region's geography is gashed by several gullies and deep ravines that run down to Keuka Lake; valleys and rolling hills used primarily as farm land; and, steep slopes on the waterfront.

It was precisely the natural beauty and rocky terrain the region prizes that would make it laborious, environmentally disruptive and almost certainly cost-prohibitive to excavate for conventional gravity sewering.

Hundreds of vacation homes (seasonal occupancy is only approximately 20-percent full-time residents) are located very close to the lake, often on small building lots with very little room for septic leach fields.  A high water table and ineffective subsurface drainage means the drain fields have poor percolation to begin with, so decline is rapid and inevitable. 

The town had required homes to be scrutinized every five years.  If an existing septic system flunked inspection, corrections were required which often included the installation of a new tank and drain field at a cost of $20,000 to $30,000 per residence. In many instances there was not enough room to put in an up-to-date replacement.

Constructing a gravity sewer system, back in 1999, was estimated to cost $6 million, whereas an E/One pressure sewer system would cost $3.2 million. The proposed LPS for the Town of Jerusalem eliminated the need for 12 lift stations with a total cost savings of $900,000. Nor did it require a rock excavation outlay pegged at $775,000.


What has Jerusalem's experience been with pressure sewer? Read the entire article on Modern Pumping Today's web site.